  3. BB101 Overheating Criteria for Schools: What Has to Pass

BB101 Overheating Criteria for Schools: What Has to Pass

Under BB101 (2018), a teaching space must not exceed its adaptive comfort limit by 1 K or more for more than 40 hours between 1 May and 30 September, in school hours, modelled with the CIBSE DSY1 2020 weather file. That is Criterion 1, and it is the only one that must be met. Criteria 2 and 3 are reported for information. Schools built to the DfE's Technical Manual (January 2026) have a stricter test: Criterion 1 plus one of Criteria 2 or 3, using a 2080 weather file. Which one applies depends on who is funding and procuring the building.

Talk to an engineer or call 0114 312 1105

This article covers new school buildings in England. BB101 also covers refurbishment, ventilation and air quality; those are mentioned only where they affect overheating.

Which test applies to your project

BB101 is the guidance that Approved Document F points to for ventilating schools. Its overheating section isn't a Building Regulations requirement: BB101 lists it as a recommended design standard, and Approved Document F makes no provision for overheating. In practice, it is set by the client's brief, the local authority, or the DfE.

BB101 (2018)DfE Technical Manual (January 2026)
Typical useLocal authority, academy trust and independent school projects that specify BB101Projects delivered under the DfE's employer's requirements
MethodCIBSE TM52 adaptive comfort, dynamic thermal modelCIBSE TM52 adaptive comfort, dynamic thermal model
Must passCriterion 1 (40 hours)Criterion 1 (40 hours) and one of Criterion 2 or 3
Weather fileCIBSE DSY1 2020, 50th percentileCIBSE DSY1 50th percentile Low Emission 2080
Future testNoneMust be able to adapt to pass with the High Emission 2080 file without changing the superstructure
Internal mechanically ventilated roomsSame adaptive criteriaOperative temperature above 25°C for no more than 3% of occupied hours

If the brief says "BB101" and nothing else, confirm in writing which version and weather file the client expects. A model run to DSY1 2020 won't satisfy a DfE reviewer.

The three criteria

All three use ΔT, the difference between the room's operative temperature and its maximum acceptable temperature, rounded to the nearest whole degree:

  • The comfort temperature is Tcomf = 0.33 Trm + 18.8, where Trm is the running mean of the outdoor temperature.
  • The maximum acceptable temperature adds the category range. For Category II (normal expectation, used for teaching spaces), that range is 3 K, so Tmax = 0.33 Trm + 21.8.
CriterionWhat it measuresLimit (BB101)
1. Hours of exceedanceHours with ΔT of 1 K or more, 1 May to 30 SeptemberNo more than 40 hours
2. Daily weighted exceedanceHours above Tmax on one day, weighted by how far aboveNo more than 6 on any day
3. Upper limit temperatureThe highest ΔT at any occupied timeΔT must not exceed 4 K

The occupied period is 09:00 to 16:00, Monday to Friday, with the summer holiday modelled as a normal term. A lunch break from 12:00 to 13:00 with no internal gains may be allowed for in classrooms (BB101). The DfE Technical Manual makes the one-hour lunch break standard.

The 40-hour limit replaces the 3% of occupied hours that TM52 uses for other buildings. For sports halls used for exams, BB101 shortens the period to 1 May to 8 July and the limit to 18 hours.

Comfort categories by space

SpaceBB101, new buildDfE Technical Manual
Teaching and learning, halls, drama, dance, examsIIII (all teaching, practical, ICT, study, libraries, halls, admin)
OfficesIIII (included in admin and staff areas)
Sports halls (not used for exams)IIIIII (with dance and activity studios)
Atria, circulation, receptionIIINot listed
Pupils with complex health needs, SENDII

Sources: BB101 Table 7.8; DfE Technical Manual Table 19.

What the DfE adds on top

The Technical Manual also sets design rules that affect the model:

  • External shading. Horizontal brise soleil on every window facing south, south-east or south-west (within 45° of due south).
  • No credit for trees. Planting around the building is encouraged, but can't be included in the final overheating model.
  • Hot surfaces. No dark-coloured materials or synthetic surfaces within 10 m of the building, and the colour of roof finishes, louvres and paving must be accounted for in the model.
  • Openable windows in every perimeter space, even where noise means the ventilation design can't rely on them.
  • Occupancy at design numbers, from the schedule of spaces, with a sensible heat gain of at least 70 W and a latent gain of at least 55 W, higher where activity is higher (CIBSE Guide A, Table 6.3). Equipment gains such as cookers in food rooms must be included.
  • Fans (ceiling or wall) are acceptable to reduce overheating, subject to a risk assessment and the school's agreement.

Ventilation and air quality limits

BB101 also sets CO₂ limits for teaching spaces, which affect window and ventilation sizing in the same model:

Ventilation modeDaily average CO₂ in occupied hoursMaximum
Mechanical, or hybrid in mechanical modeBelow 1,000 ppmNo more than 1,500 ppm for more than 20 consecutive minutes a day
Natural, or hybrid in natural modeBelow 1,500 ppmNo more than 2,000 ppm for more than 20 consecutive minutes a day

As a starting point before modelling, BB101 suggests openable windows or vents with an effective area of at least 3% of the floor area, which can mean a physical opening of around 5%. The model then confirms whether that's enough.

Usual reasons a classroom fails

  • Large south- or west-facing glazing without external shading.
  • Single-sided ventilation with restricted window openings, often because of security or noise.
  • High-level openings missing, so hot air builds up under the ceiling. BB101 also limits radiant asymmetry from hot ceilings in single-storey teaching spaces to 5 K.
  • ICT and equipment gains underestimated, or occupancy below the design number.
  • Low thermal mass and no night cooling.
  • A model run with the wrong weather file for the brief.

BB101 says mechanical cooling should not normally be needed in general teaching spaces with ICT gains below 15 W/m², or 25 W/m² in practical spaces. Where cooling is used, it should be justified on heat load and energy grounds.

Before the overheating model: a checklist

  1. Confirm which test the client requires: BB101 2018, the DfE Technical Manual, or a project-specific brief.
  2. Confirm the weather file in writing.
  3. Get the schedule of spaces with design occupancy for every room.
  4. Get the ICT and equipment gains, including cookers and kilns.
  5. Get window types, opening angles, restrictors and effective areas.
  6. Agree the ventilation strategy for each space type: natural, hybrid or mechanical.
  7. Check external shading on south, south-east and south-west elevations.
  8. Model every occupied space, and report Criteria 1, 2 and 3 for each.
  9. Run the CO₂ check in the same model.
  10. Report any failures with the mitigation options tested.

More on the service: BB101 overheating assessments for schools and DfE energy assessments for schools.

Questions

FAQs

Does a school have to pass all three BB101 criteria?

Under BB101 (2018), no: only Criterion 1 must be passed, and Criteria 2 and 3 are reported for information. Under the DfE Technical Manual (January 2026), Criterion 1 must be met plus one of Criterion 2 or 3.

Which weather file is used for a BB101 assessment?

BB101 (2018) uses the CIBSE DSY1 2020 file (50th percentile) most appropriate to the school's location, which isn't always the nearest. DfE Technical Manual projects use DSY1 50th percentile Low Emission 2080, and must be able to adapt to pass with High Emission 2080.

Is BB101 the same as TM52?

It uses the TM52 method, but with school hours, the summer holiday modelled as occupied, and a fixed 40-hour limit for Criterion 1 instead of TM52's 3% of occupied hours.

Does BB101 overheating apply to refurbishments?

Yes, but with lower comfort categories. BB101 allows Category III, or IV where III isn't practical, for teaching spaces in refurbished buildings, provided comfort is no worse than before.

Get the overheating model in early

Send us the plans, sections, elevations, window schedule and the schedule of spaces, and tell us which brief applies. We'll model every occupied space, report all three criteria and the CO₂ check, and test the mitigation before the design is fixed. Fee proposal within one working day.

Talk to an engineer

Accredited by

CIBSE Low Carbon Energy AssessorCIBSE Low Carbon ConsultantElmhurst Energy Approved

Get in touch

Send drawings, fee proposal within 1 working day.

Office address
Spaces Acero, 1 Concourse Way, Sheffield, S1 2BJ
How we use your details